Lesson notesDomain 7: Trees and Construction · 9% of the exam
Tree protection plans through the construction phases
Reading site plans, the phases of construction, who is responsible for what, coordinating with contractors, and checking the plan works.
Key points
PhasesPlanning, design, preconstruction, construction, post-construction; protection is needed in every one.
Site plansMark trees and TPZs; check limits of disturbance, grades, utilities, access, staging and storage.
RolesOwner/developer commits and funds; design team designs around trees; contractors build to the plan; project arborist advises, inspects, documents.
CoordinationPreconstruction meeting, contract requirements and penalties, scheduled inspections.
EffectivenessDocument tree condition before, during and after to assess the plan.
Covered in the full lesson
- Planning
- Design
- Preconstruction
- Construction
- Post-construction
Quick check
An exam-style question on this lesson. Open it to see the answer and why.
When should trees first be considered in a construction project?
- In the planning phase
- During construction
- After construction
- Only if a tree is damaged
Answer: A. Early inventory lets the design work around valuable trees.
The full lesson adds more
In ArboristPass this lesson has a narrated video, five exam-style questions, a sorting drill, flashcards and a printable study sheet, and the course ends with 3 full mock exams.
Previous: Tree protection zones and critical root zones · Next: Treating construction-damaged trees